Downtown Construction Update – July 12
Main St. Waterville
Two-Week Construction Look Ahead

July 12:

Crooker- Finish fine grading of the left side of Main Street.

A/D Electric – Remove temporary lights from Common Street to Silver Street. Continue conduit on Front Street median.

July 13:

Crooker – Paving left of Main Street – Spring Street to Temple Street. Begin demolition of CMP duct bank on Front Street.

July 14-16:

Crooker -CMP duct bank replacement.

KMP- Install curb on the left of Front Street and the left of Main Street.

July 19-23:

Crooker – CMP duct bank replacement.

KMP – Finish curb installation on the left of Main Street to Temple Street.